单一煤层高位瓦斯抽采巷道布置位置研究

Study on Layout of High Gas Extraction Roadway in Single Coal Seam

  • 摘要: 以常村煤矿2103工作面为工程背景,在煤层开采方向,通过分析煤层基本顶的受力状态,建立基本顶岩梁断裂前夕的力学模型,求解出基本顶的周期垮落步距;利用垮落步距,引入渗透率公式,重新建立力学模型,求解岩梁内部渗透率的分布状况,并按照渗透率分类标准,将高位瓦斯抽采巷道布置在煤层透气性较好的区域。在煤层倾斜方向,建立二维模型,确定出剪切破坏带的边界,通过分析将瓦斯抽采巷道布置在剪切破坏带以外。最终确定将瓦斯抽采巷道布置在轨道运输平巷上方27.03 m,与轨道运输平巷内错29.82 m的掘进方案。给出了高位瓦斯抽采巷道实际测得的瓦斯抽采量和巷道的变形特征,表明所设计的高位瓦斯抽采巷道的位置合理,能够保证煤矿安全生产需求。

     

    Abstract: This paper took 2103 working face of Changcun Coal Mine as the engineering background, by analyzing of the stress state of the basic roof along the mining direction of coal seam, set up the mechanical model of the basic roof before the rock beam broke, and the periodic collapse step distance of the basic roof was solved; by using the collapse step distance, the permeability formula was introduced to rebuild the mechanical model and solve the distribution of internal permeability of rock girder, and the high level gas drainage roadway was arranged in the area with good gas permeability of coal seam according to the permeability classification standard. The boundary of shear failure zone was determined by establishing a two-dimensional model along the inclination direction of coal seam. The gas extraction roadway was arranged outside the shear failure zone through analysis. To sum up, the tunneling scheme was determined that the gas extraction roadway was arranged 27.03 m above the rail transport roadway and 29.82 m inner alternated with it.The actual measured gas drainage and the deformation characteristics of the roadway were given. The results showed that the location of the high gas drainage roadway is reasonable, which can ensure the safety production demand of coal mine.

     

/

返回文章
返回